Back to Interim compensation orders, 1987 to 1988
The story of Interim compensation orders, 1987 to 1988
The Bhopal District Judge ordered Union Carbide Corporation to deposit Rs 350 crore as interim compensation in December 1987; the Madhya Pradesh High Court cut it to Rs 250 crore in April 1988; both sides appealed to the Supreme Court, which led to the settlement.
17 Dec 1987 โ 4 Apr 1988
Interim compensation orders, 1987 to 1988. The Bhopal District Judge ordered Union Carbide Corporation to deposit Rs 350 crore as interim compensation in December 1987; the Madhya Pradesh High Court cut it to Rs 250 crore in April 1988; both sides appealed to the Supreme Court, which led to the settlement.
4 Apr 1988
Madhya Pradesh High Court intervened in Interim compensation orders, 1987 to 1988. Cut the interim compensation to Rs 250 crore.
3 sourced connections, each with its evidence. Open the explorer to follow any of them further, filter by lens, or move through time.
Drawn from the sourced links on Interim compensation orders, 1987 to 1988. Change a link and this story changes with it.